Period |
Activities |
Outputs |
|
Nov, 2010 |
Identifying, screening, and selecting
FOTs |
Project team contracted |
|
Dec, 2010 |
Development of research instruments and
action plan
|
·
Detailed Research Design
·
Research Instruments, including
questionnaire and FGD outlines
·
Research Action Plans detailing roles
and responsibilities, timelines, and
itineraries for the FOTs
|
|
Jan, 2011 |
·
Conducting spadework including
establishing contacts, securing
cooperation and essential information
from local governments
·
Training Field Supervisors
·
Conducting FGDs and pre-testing to
refine questionnaire
|
Spadework for research complete |
|
Feb, 2011 |
Undertaking Survey and FGDs according to
Research Design
|
Survey and FGDs completed and data
captured
|
|
Mar–Apr, 2011 |
·
Data entry, verification & processing
·
Analysis of captured data and
dissemination of preliminary findings
amongst project stakeholders
|
·
Data cleaned, stored and ready for
analysis
·
Preliminary Report Prepared and
circulated |
|
May-July, 2011 |
·
Detailed analysis of captured data
·
Preparation and dissemination of Final
Report
·
Formatting of Final Report into a
Special Report format for publishing by
the USIP
|
·
Final Report prepared and disseminated
amongst project stakeholders
·
Special Report published by USIP
|
|
Aug-Nov, 2011 |
Conducting Dissemination Seminars in
Islamabad, Lahore, Karachi, Peshawar, &
Quetta
|
5 Seminar Reports detailing the
attendance and proceedings for these
events |